Dynamic load management for car parks

More charging points. Without increasing the building's power.

BMA distributes the building's free power between charging stations in real time — without exceeding the site limit.

Illustrative example. Values are notional.

Where the limit appears

The problem begins with scale

  1. 10 there is still headroom
  2. 50 the power runs out
  3. 100+ a different control principle is needed

Illustrative example. A specific site is calculated from actual loads and supply parameters.

Counted by nameplate

100 × 7 kW = 700 kW

But cars stand for 8–12 hours and never need 700 kW all at once. What is needed is not a sum of nameplates but management of the available power.

The limit is not created by the charging station but by the free power of the specific building. While there is spare capacity, connection is routine; the refusal goes to whoever asks once the margin is used up.

Solution

Not a fixed limit, but a live energy balance of the building

Every building has a permitted capacity granted at grid connection. In practice the building almost never uses all of it, and at night it consumes noticeably less. That difference is already connected to the grid — BMA hands it to the charging stations to exactly the extent it is free at that moment.

Permitted capacity of the site · 600 kW 13:00
Time
Building load
Available for charging
Per car
Cars connected: 40

Day

By day, charging runs at reduced power

The building consumes more → charging power falls.

Evening peak

At the peak, the total stays within the site limit

BMA automatically limits the charging load.

Night

At night, the cars get the maximum

The building unloads → charging power rises.

Without load management

  • Each point counts at nameplate and is added to the building's design load
  • Only a few stations can be connected — while the input has spare capacity
  • Further growth requires more connected capacity: a substation, approvals, months

With BMA Dynamic Load Management

  • The power budget is recalculated at every change of the building load
  • Power is distributed between cars automatically, via each station's current limit
  • The number of points grows with demand — within the site's energy window

Available charging power = permitted capacity of the site − current building load − technical reserve

Illustrative example. Notional site: permitted capacity 600 kW, technical reserve 40 kW, 40 cars connected, stations up to 7 kW; in “No management” mode a notional fixed cap of 60 kW is shown. Algorithms, measurement frequency and the size of the reserve are defined by the supply architecture of the specific site. This is not a calculation of a real building and not a promise of a specific number of stations or charging speed.

How BMA works

Five actions the system performs continuously

One continuous cycle: it never stops while at least one car is plugged in.

  1. Measures

    The current building load at the main input — all consumption, per phase, in real time.

  2. Calculates

    The actually free power, taking the technical reserve into account.

  3. Distributes

    The available power between the connected cars — each station gets its own current limit.

  4. Recalculates

    The limits at every change of the building load.

  5. Protects

    The site from exceeding its permitted capacity: stations can only reduce the load, never raise it.

Control is by current: each station is given its own current limit. The station passes that limit to the car over the signalling line in the charging cable and holds it, so the total stays within the budget.

Algorithms, measurement frequency and the size of the reserve are defined by the supply architecture of the specific site.

Architecture

Control runs on site, not on the internet

The power balance is calculated locally, in the load controller. The cloud handles metering and monitoring but is not part of the control loop.

  1. 1Energy flows through the power circuit: grid → switchboard → controller → stations → cars
  2. 2Measurement at the switchboard sends the current building load to the controller
  3. 3The BMA Controller calculates the free power
  4. 4The controller sets the permitted current for the stations
  5. 5Power is redistributed between the cars

What happens when the cloud connection is lost

The balance and the station setpoints are produced in the cabinet on site. If the cloud link drops, power distribution continues unchanged — only data transfer pauses: session history and accounts update once the link is back.

If a station loses contact with the controller, it falls back to a preset minimum or switches off. So the permitted capacity of the site cannot be exceeded under any scenario. The site limit can also be set externally — from the grid operator's account.

Illustrative example. Values are notional.

One BMA system

One manufacturer is responsible for the station, the algorithm and the control

The station, the algorithm and the control channel are the responsibility of one BMA system. That is why the guarantee of staying within the limit rests on the architecture, not on settings.

  • BMA Charging Station

    Charging point that holds the permitted current.

  • BMA Dynamic Load Controller

    Local measurement and calculation of the available power.

  • BMA Cloud

    Monitoring, metering and digital services.

Building cross-section: main switchboard, BMA distribution unit and charging stations in the underground car park 1Building switchboard2BMA Dynamic Load Controller3BMA charging stations

Scaling

From a few points to a large car park — without replacing equipment

The same system grows with the car park.

  1. 1 cabinet · 9 or 15 points

    Two versions of the load controller.

  2. Several cabinets

    One master module, the rest slaves.

  3. New station groups

    Transition by cabinet firmware; the stations at the spaces stay in place.

  4. Large car park

    The number of points grows with demand within the available power.

The equipment set, the measurement scheme and the distribution of points across phases are defined by the project after a technical site survey.

Applications

Where cars park for long and spaces are assigned

The effect is greatest when a car stays in place for 8–12 hours while the building load is at its lowest.

Residential district with car parks and charging stations
Residential complexes and apartments Closed car park, assigned spaces, overnight parking. Charging at your own space with individual metering — the core BMA scenario.
  • Business centres

    Daytime parking for staff and tenants within the building's power.

  • Corporate car parks

    Company and staff vehicles; priorities and limits set by configuration, not by hardware.

  • Mixed-use buildings

    Housing, offices and services on one main input: one energy balance for the whole site.

  • Hotels

    Overnight guest parking. Suitable where spaces are assigned to rooms or the hotel controls access to the point; otherwise the access scenario is designed separately.

Who gets what

Four parties — one circuit

  • Owner, developer

    More charging points without automatically increasing the site's capacity.

  • Management company

    Sees the load and the state of every point.

  • User

    Charges at their own space with individual metering.

  • Grid operator

    Gets an observable and manageable charging load.

Company

Behind the solution is a working production facility

BMA GreenPower is the charging-infrastructure division of the Terra-Tok engineering group: in-house production of electrical equipment and busbar systems.

  • 2013 engineering group founded
  • 5,000 m² of own production space
  • 100+ engineers, designers and developers
  • 700+ busbar-system projects
  • Engineering centre
  • Test laboratory
  • Own production lines
  • KEMA certification of the group's products

We develop and manufacture the whole chain ourselves — the charging station, the load controller and the cloud software. It is not an assembly of third-party components and not an add-on to someone else's equipment.

Certificates, technical documentation and a reference list are provided on request.

BMA GreenPower charging stations

First step

Let us assess your site

We will give a preliminary estimate of how many charging points can be placed with dynamic load management and what source data the calculation needs.

What the calculation needs

  1. Supply diagram and permitted capacity of the site
  2. Number of parking spaces and desired number of charging points
  3. Actual load profile — if there is no data, it is recorded during the site survey

Email: sales@bma-gp.com Phone: +7 (343) 226-77-40

Email or phone is enough

Additional (optional)